Lendware Adoption Dashboard

Track progress and manage the adoption action plan

Total Tasks
34

Across 2 versions

Completed
2

6% complete

In Progress
2

28 not started

Health Status
on track

2 blocked tasks

Version Progress
Completion status by version milestone
v10/8 tasks
0 done0 in progress8 pending
v0.52/26 tasks
2 done2 in progress20 pending
Owner Progress
Task completion by team member
Tim0/9 tasks
0 done0 in progress9 pending
Spencer2/25 tasks
2 done2 in progress19 pending
v0.5
Target: 3/14/2026

Target mid March 2026

Key Outcomes:

  • Baseline adoption view that is usable for leadership updates. not perfect, but defensible.
  • Cost leak reduced. noisy tracking trimmed. session replay controlled.
  • Company reporting direction set. start moving cohorts → groups.
v1
Target: 4/14/2026

Target April 2026

Key Outcomes:

  • Group Analytics fully replaces cohorts for company rollups. nesting works.
  • Custom events and standardized properties make metrics decision grade.
  • MongoDB integration completed so historical and inactive user visibility is accurate.
  • Segment views ship. power user vs set it and forget it dashboards.